Roofing crew replacing a ballasted EPDM rubber roof with a white TPO membrane on a large commercial building

Reroofing a Ballasted Rubber Roof with TPO

10/5/26, 2:00 PM

Single Ply, TPO, Ballaster Rubber

Is your ballasted rubber roof at the end of its life? In this project video, Insulated Roofing Contractors (IRC) replaces a 150,000-square-foot ballasted EPDM roof with a mechanically fastened TPO membrane, completing the entire commercial reroof in less than 30 days.

Step 1: Remove the ballast


Ballasted EPDM roofs are held down by tons of loose river rock. Our crews removed all of the stone to expose the old rubber membrane underneath.

Step 2: Tear off the old rubber membrane


With the ballast gone, the aging EPDM was removed down to the substrate, giving us a clean surface to build the new roof system on.


Step 3: Install mechanically fastened TPO
The new TPO membrane was mechanically fastened to the roof deck. TPO's heat-welded seams create a strong, watertight bond, and its white, reflective surface helps lower cooling costs.


Why replace ballasted EPDM with TPO?

  • Less weight on your structure. Removing the rock takes significant load off the building.

  • Easier leak detection. With no ballast covering the membrane, problems are easy to spot and repair.

  • Stronger seams. Heat-welded TPO seams outperform the taped or glued seams on older rubber roofs.

  • Energy savings. A reflective TPO roof reflects sunlight instead of absorbing heat.

Large-scale reroofing, done fast
Finishing a 150,000-square-foot reroof in under 30 days takes experienced crews and tight project management. With 120+ crews nationwide, IRC has the capacity to complete large commercial roof replacements quickly while keeping your building running. Contact IRC to get a quote on your roof replacement.