Stone Mountain Distribution Center
850,000 sq ft reroof. Zero missed shipments.
Distribution & Warehouse
Single-Ply
500,000+ sq ft
850,000 sq ft full tear-off to the metal deck
Nearly 2,000 skylights replaced
24/7 facility with zero downtime
48,508 labor hours
Zero injuries, zero incidents, zero property damage
20-year manufacturer warranty
The Challenge
The Stone Mountain Distribution Center is a critical hub in its supply chain. At 850,000 square feet, it runs around the clock with loading docks active, trailers moving and East Coast retail shipments flowing without interruption. The roof had reached the end of its life, and the fix wasn’t simple. It needed a full tear-off to the metal deck and nearly 2,000 new skylights, and the work had to happen during peak holiday fulfillment season. Any delay, safety breach or interference wouldn’t just be an inconvenience. It would hit the supply chain directly.
The Scope
Full tear-off to the metal deck
Vapor retarder and two layers of XPS insulation
Mechanically attached DensDeck
80mil Sarnafil S327 single-ply membrane
Nearly 2,000 Velux skylights replaced
20-year manufacturer warranty
The Approach
IRC built a plan around the distribution center’s needs, not the other way around. A dual-crew strategy, with tear-off at night and installation during the day, kept progress moving without touching daily operations. Every night, crews cleared and swept the work area so dock activity could resume first thing each morning.
To keep trailers moving, IRC put its own CDL-licensed drivers into the facility’s dispatch rotation, moving trailers in and out of bay doors as needed throughout the project. Controlled access zones were marked every night, and IRC’s own man-lifts and yard tug meant the jobsite never had to borrow the facility’s equipment.
The Result
Stone Mountain got a brand-new 850,000 square foot roof without missing a single shipment. Through multiple retail seasons, including the busiest holiday fulfillment window of the year, the facility ran exactly as it always had: 48,508 labor hours, zero injuries, zero property damage and zero disruption. The project was nominated for the Sika Roofing Job of the Year, and the nomination called IRC’s crews innovative, safety-minded and exceptional performers.
“Their company was able to continue work throughout the season without delay to the client’s tight delivery or shipment schedule... they delivered a high-quality roof, with zero incidents, zero property damage, and exceeded our already high expectations.”
— Rob Bland